WEEK 7: Hallelujah...Hallelujah...(sing along)

This week we are finally seeing some movement after a series of plumbing and forming inspections. It seems like this is going to be a constant activity each week. Here is where we left you last week:


In somewhat of a surprise, after missing a few days because of family friends visiting us, and a short trip to scenic Sedona, we returned to find that most of the post-tensioning wiring and rebar had been installed while we were gone. BTW, if you've never had an opportunity to visit Sedona, it is a 'must do' on your bucket list. Incredible environmental landscape and some decent wine, to boot! A "gotta do" trip!


In this picture, the red cable is the post-tensioning wire which will be tightened to a specific load level once the concrete is poured as a foundation slab. The outside footers, which aren't clearly visible, are about 12" deep, so this foundation won't be going anywhere soon.


We were generally impressed with how straight and precise the cabling is set, and where the tensioning points are located.


Now that the cabling and foundation rebar is set, there are a couple more inspections before we can pour concrete next week.


So slowly, but surely, we are finally making visible progress. Also this week we f=have finalized the pool, hardscape and font and back landscape plan, so thankfully that is out of the way for now. See y'all next week!